Budgets and burn
Hours logged against each project's budget, with the forecast at the end date.
Over budget
2
229.3 h over in total
At risk
1
Forecast above budget
Active projects
7
16 people logging
Billable
70%
Last 12 weeks
Budget vs logged
Forecast: logged hours plus the last four weeks' average until the end date.
- Budget
- Logged
- Forecast
114%
1,486 of 1,300 h
186 h over budget
Forecast 1,874 h · 96.9 h/week
SP
NV
SV
HR
105%
983.3 of 940 h
43.3 h over budget
Forecast 1,175 h · 63.8 h/week
JM
HR
GR
TW
75%
1,538.8 of 2,050 h
511.3 h left
Forecast 2,248 h · 101.3 h/week
JI
TK
JZ
RB
53%
1,221.5 of 2,300 h
1,078.5 h left
Forecast 2,067 h · 76.9 h/week
GR
RB
JI
FC
42%
1,271.8 of 3,030 h
1,758.3 h left
Forecast 2,573 h · 86.8 h/week
XC
DG
TK
JM
41%
905.5 of 2,210 h
1,304.5 h left
Forecast 2,096 h · 56.7 h/week
NV
JF
SV
SP
20%
1,920.3 of 9,430 h
7,509.8 h left
Forecast 8,482 h · 123.8 h/week
JG
TW
FC
JF