Beacon mobile app

Swiss Post · managed by Samuel Vuadens · ends 11 Dec 2026

Over budget
Budget

1,300 h

Whole project

Logged

1,486 h

114% of the budget

Over budget

186 h

4 weeks left

Forecast

1,874 h

Above budget at this pace

Weekly burn

96.9 h

4 weeks left

People

7

Logged on this project

Burn-up
Cumulative hours against the budget, week by week.
Hours per week
Average 96.9 h over the last four weeks.
Who works on it
Hours per person since the start of the history.
SP

Sandro Pereira

Software Engineer · 29% of the project

432 h

NV

Nicolas Varone

Frontend Engineer & UI/UX Designer · 23% of the project

346 h

SV

Samuel Vuadens

Chief Product Officer · 21% of the project

311 h

HR

Helder Ribeiro

Software Engineer · 17% of the project

247 h

TW

Thomas Winter

Chief Commercial Officer · 5% of the project

71 h

JG

Jean-Pierre Gehrig

Chief Executive Officer · 4% of the project

60 h

JF

Justin Fournier

Young Padawan · 1% of the project

20 h

Latest entries
SP

Sandro Pereira

Mon 16 Nov

7 h

NV

Nicolas Varone

Mon 16 Nov

5 h

HR

Helder Ribeiro

Mon 16 Nov

4 h

SV

Samuel Vuadens

Mon 16 Nov

3.5 h

TW

Thomas Winter

Mon 16 Nov

3 h

JF

Justin Fournier

Mon 16 Nov

3 h

JG

Jean-Pierre Gehrig

Mon 16 Nov

1.75 h

NV

Nicolas Varone

Fri 13 Nov

6.25 h

SP

Sandro Pereira

Fri 13 Nov

6 h

SV

Samuel Vuadens

Fri 13 Nov

4.25 h

HR

Helder Ribeiro

Fri 13 Nov

3.75 h

TW

Thomas Winter

Fri 13 Nov

2.25 h